Positive materials removed from a hillside house before it is demolished
Example project
- Home
- 1960s single-story house on a hillside lot in Rancho Palos Verdes
- Original request
- Take the house down and rebuild on the same lot
- Testing
- A whole-house survey by a Cal/OSHA-certified asbestos consultant, about 30 samples from ceilings, floors, walls and ducts
- Found
- Asbestos in the ceiling texture throughout, the floor tile in the kitchen and baths and the wrap on the duct runs under the house
- Clear
- The wall compound and the window putty
- Area
- About 1,100 sq ft of ceiling, 300 sq ft of floor and 120 ft of duct wrap
- Timeline
- Notice no later than 10 working days ahead, then six working days before the wrecking crew
- Cost
- $27,000
In this example, a family on a hillside lot in Rancho Palos Verdes is replacing a 1960s house. The city’s FAQ asks demolition applicants to get clearance from the district before applying for the city permit, and what the district takes is a Rule 1403 notification, filed online by the abatement contractor.